Greenwich Tideway, London

Client – Szerelmey Restoration Ltd.

Location – Greenwich Pumping Station, Greenwich High Road, London.

Scope – Designed access scaffolding for remedial and refurbishment works.

Materials Used – Tube and fittings, Fire Retardant Debris Netting and Plastic Sheeting, 750mm Apollo X Beams.

Duration – 16 weeks.

Watford Scaffolding Ltd were engaged to deliver  a fully designed access scheme of traditional tube & fitting. For quite a small building the scaffold had to be bridged in 3 area’s to avoid loads going onto roof’s. The bridges ranged from 14m to 22m in length. The works consisted of new lead work to the high level lantern, new window installation, brickwork with stone repairs, and a full façade steam clean. One elevation was fully bridged with the access scaffold suspended, or  “hung”. For quite a small project there was a large amount of design input required in order for the smooth delivery. All “Delivered Safety First” and to programme.