Bolanachi Building, Bermondsey
Client – Kier.
Location – Bermondsey, London.
Scope – Full design scaffolding for façade de-cladding and replacement.
Materials Used – Layher LW Allround System Scaffold, Layher System Staircases, Fire Retardant Debris Netting, 450mm Haki Beams and 750mm Apollo X Beams.
Duration – 36 weeks.
WSL were engaged with early to deliver a full system access scaffold for de-cladding works. The works entailed an external courtyard and internal atrium. The building remained occupied throughout the duration of the project and arrangements were made to reduce the impact on residents and local stakeholders. The internal scaffold was designed to be completely freestanding to enable full access to facades.